NEWS

PRACC UPDATE ELEVEN

Mullions are erected in the Sports Hall and retaining walls and stairs are completed at ovals edge.

 

PRACC UPDATE TEN

Upper wall framing is complete including the additional of cross-bracing in the end two bays at the East and West ends of the Sports Hall. 

 

PRACC UPDATE NINE

Production of bearers and joists in the Timber Built factory, Melbourne (VIC).

 

PRACC UPDATE EIGHT

Pre-assembled upper wall framing units are lifted into position via crane.

 

PRACC UPDATE SEVEN

The portal frames were delivered in five pieces and assembled on site. In one working day the columns were raised and secured, purlins were then fitted to rafter pairs and lifted into position fully assembled. The purlins for the three remaining even bays were fitted from scissor lifts.